Legislation – The Five Estuaries Offshore Wind Farm Order 2025
PART 3Streets
Power to alter layout etc. of streets17.
(1)
Subject to paragraphs (2) and (3), the undertaker may, in so far as may be expedient or necessary for the purposes of or in connection with constructing, operating or maintaining the authorised development, alter the layout of any street and, without limitation on the scope of this paragraph, the undertaker may—
(a)
alter the level or increase the width of the street including any kerb, footway, cycle track or verge; and
(b)
make and maintain passing place(s).
(2)
The undertaker must restore any street that has been temporarily altered under this article to the reasonable satisfaction of the street authority.
(3)
The powers conferred by paragraph (1) must not be exercised without the consent of the street authority.
(4)
If a street authority fails to notify the undertaker of its decision within 56 days of receiving an application for consent under paragraph (5), that street authority is deemed to have granted consent.