Legislation – The Five Estuaries Offshore Wind Farm Order 2025

New Search

Introduction

PART 1
Preliminary

1 Citation and commencement

2 Interpretation

PART 2
Principal Powers

3 Development consent etc. granted by the Order

4 Operation of generating station

5 Deemed marine licences under the 2009 Act

6 Power to maintain the authorised development

7 Benefit of the Order

8 Application and modification of legislative provisions

9 Defence to proceedings in respect of statutory nuisance

PART 3
Streets

10 Street works

11 Application of the 1991 Act

12 Construction and maintenance of new or altered highway

13 Temporary closure of public rights of way

14 Temporary restriction of use of streets

15 Access to works

16 Traffic regulation

17 Power to alter layout etc. of streets

PART 4
Supplemental powers

18 Discharge of water

19 Authority to survey and investigate the land

20 Protective work to buildings

PART 5
Powers of acquisition

21 Compulsory acquisition of land

22 Time limit for exercise of authority to acquire land compulsorily

23 Compulsory acquisition of rights

24 Compulsory acquisition of land: minerals

25 Private rights

26 Application of the 1981 Act

27 Acquisition of subsoil only

28 Modification of Part 1 of the 1965 Act

29 Rights under or over streets

30 Temporary use of land for carrying out the authorised development

31 Temporary use of land for maintaining the authorised development

32 Statutory undertakers

33 Recovery of costs of new connections

34 Funding

PART 6
Miscellaneous and general

35 Application of landlord and tenant law

36 Felling or lopping of trees and removal of hedgerows

37 Trees subject to tree preservation orders

38 Abatement of works abandoned or decayed

39 Saving provisions for Trinity House

40 Crown rights

41 Protective provisions

42 Application of the 1990 Act

43 Certification of plans, etc.

44 Service of notices

45 No double recovery

46 Requirements

47 Arbitration

48 Compensation

SCHEDULES

SCHEDULE 1 Authorised development

SCHEDULE 2 Requirements

SCHEDULE 3 Streets subject to street works

SCHEDULE 4 Traffic Regulation

SCHEDULE 5 Access to works

SCHEDULE 6 Land of which temporary possession may be taken

SCHEDULE 7 Land in which only new rights etc. may be acquired

SCHEDULE 8 Modification of compensation and compulsory purchase enactments for creation of new rights and imposition of restrictive covenants

SCHEDULE 9 Protective provisions

SCHEDULE 10 Deemed marine licence – Generation Assets

SCHEDULE 11 Deemed marine licence – Transmission Assets

SCHEDULE 12

SCHEDULE 13 Compensation

SCHEDULE 14 Arbitration rules

SCHEDULE 15 Documents to be certified

SCHEDULE 16 Offshore co-ordinates

Signature

Explanatory note

PART 4Supplemental powers

Discharge of water18.

(1)

Subject to paragraphs (3) and (4) below the undertaker may use any watercourse or any public sewer or drain for the drainage of water in connection with the carrying out or maintenance of the authorised development and for that purpose may inspect, lay down, take up and alter pipes and may, on any land within the Order limits, make openings into, and connections with, the watercourse, public sewer or drain.

(2)

Any dispute arising from the making of connections to or the use of a public sewer or drain by the undertaker pursuant to paragraph (1) is determined as if it were a dispute under section 106 (right to communicate with public sewers) of the Water Industry Act 199141.

(3)

The undertaker must not discharge any water into any watercourse, public sewer or drain except with the consent of the person to whom it belongs; and such consent may be given subject to such terms and conditions as that person may reasonably impose, but must not be unreasonably withheld.

(4)

The undertaker must not carry out any works to any public sewer or drain pursuant to paragraph (1) except—

(a)

in accordance with plans approved by the person to whom the sewer or drain belongs, but such approval must not be unreasonably withheld; and

(b)

where that person has been given the opportunity to supervise the making of the opening.

(5)

The undertaker must not, in carrying out or maintaining works pursuant to this article, damage or interfere with the bed or banks of, or construct any Works in, under, over or within eight metres of, any watercourse forming part of a main river, or within 16 metres of a tidally influenced main river without the prior written consent of the Environment Agency.

(6)

The undertaker must take such steps as are reasonably practicable to secure that any water discharged into a watercourse or public sewer or drain pursuant to this article is as free as may be practicable from gravel, soil or other solid substance, oil or matter in suspension.

(7)

This article does not authorise the entry into controlled waters of any matter whose entry or discharge into controlled waters is prohibited by regulation 12 (requirement for an environmental permit) of the 2016 Regulations.

(8)

In this article—

(a)

public sewer or drain” means a sewer or drain which belongs to a sewerage undertaker, the Environment Agency, an internal drainage board or a local authority; and

(b)

other expressions, excluding watercourse, used both in this article and in the 2016 Regulations have the same meaning as in those Regulations.

(9)

If a person who receives an application for consent or approval fails to notify the undertaker of a decision within 28 days of receiving an application for consent under paragraph (3), or approval under paragraph (4)(a) that person is deemed to have granted consent or given approval, as the case may be.

41