Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.
Part 3Development and nature recovery
Powers and duties: Natural England etc
86Powers of entry: compensation
(1)
If damage is caused to land or other property in the exercise of a power of entry, a person suffering the damage may recover compensation from Natural England.
(2)
(3)
Any question of disputed compensation under subsection (1) is to be referred to and determined by the Upper Tribunal.
(4)
Section 4 of the Land Compensation Act 1961 (costs) applies to the determination of a question referred under subsection (3) as it applies to the determination of a question under section 1 of that Act, but as if references to the acquiring authority were references to Natural England.