Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.
Part 2Other taxes
Electricity generator levy
21New investment exemption
(1)
Part 5 of F(No.2)A 2023 (electricity generator levy) is amended as follows.
(2)
In section 280 (key concepts), in subsection (1), in the definition of “relevant” (as in relevant generating station)—
(a)
omit the “and” after paragraph (a), and
(b)
“, and
(c)
to the extent it is not comprised of qualifying new generating plant (see section 311A);”.
(3)
“311AMeaning of “qualifying new generating plant”
(1)
Generating plant is “qualifying new generating plant” if it is new generating plant commissioned as part of a qualifying project that meets the new investment condition.
(2)
The new investment condition is met in relation to a qualifying project if on 21 November 2023 it was reasonable to conclude, having regard to all of the circumstances, that there is a significant likelihood of the project not proceeding.
(3)
The Treasury may by regulations provide for cases in which qualifying projects are to be treated as meeting the new investment condition.
(4)
“Qualifying project” means a project to commission—
(a)
new generating plant for—
(i)
a new generating station, or
(ii)
an existing generating station which (as a result of the project) is to be wholly or substantially comprised of new generating plant, or
(b)
new generating plant that increases the generating capacity of an existing generating station.
(5)
Subsection (6) applies where new generating plant that increases the generating capacity of an existing generating station replaces existing generating plant.
(6)
Only so much of the new generating plant as represents generating capacity in excess of the capacity of the generating plant it replaces is to be regarded as qualifying new generating plant.”
(4)
“qualifying new generating plant