Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.
PART 6INFRASTRUCTURE CONSENT ORDERS
Provision in orders authorising compulsory acquisition
65Land to which authorisation of compulsory acquisition can relate
(1)
An infrastructure consent order may include provision authorising the compulsory acquisition of land only if—
(a)
the land is in Wales or the Welsh marine area, and
(b)
the Welsh Ministers are satisfied that one of the conditions in subsections (2) to (4) is met.
(2)
The condition is that the application for infrastructure consent included a request for compulsory acquisition of the land to be authorised.
(3)
The condition is that all persons with an interest in the land consent to the inclusion of the provision.
(4)
The condition is that the procedure specified in regulations for the purpose of this section has been followed in relation to the land.