Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.
PART 3APPLYING FOR INFRASTRUCTURE CONSENT
Application procedure
38Notice of persons interested in land to which compulsory acquisition request relates
(1)
This section applies where—
(a)
the Welsh Ministers have accepted an application for infrastructure consent as valid, and
(b)
the application includes a request to authorise compulsory acquisition of land or of an interest in or right over land (a “compulsory acquisition request”).
(2)
The applicant must give to the Welsh Ministers a notice specifying the names, and such other information as may be specified in regulations, of each affected person.
(3)
Notice under subsection (2) must be given in the form and manner specified in regulations.
(4)
A person is an “affected person” for the purposes of this section if the applicant, after making diligent inquiry, knows that the person is interested in the land to which the compulsory acquisition request relates or any part of that land.