Legislation – Planning and Infrastructure Act 2025
Changes to legislation:
There are currently no known outstanding effects for the Planning and Infrastructure Act 2025, Section 112.![]()
Changes to Legislation
Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.
Part 5Compulsory purchase
112Temporary possession of land in connection with compulsory purchase
“(3)
Subject to—
(a)
any express provision in another Act;
(b)
any provision in an order granting development consent made under section 114 of the Planning Act 2008;
(c)
any provision in an order made under section 1 or 3 of the Transport and Works Act 1992;
(d)
any provision in an order granting infrastructure consent made under section 60 of the Infrastructure (Wales) Act 2024 (asc 3);
the power in subsection (2) is the only power under which a person may take temporary possession of land compulsorily.”