Legislation – Planning and Infrastructure Act 2025
Changes to legislation:
There are currently no known outstanding effects for the Planning and Infrastructure Act 2025, Paragraph 2.![]()
Changes to Legislation
Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.
Schedule 3Environmental delivery plans: effect on environmental obligations
Protected sites: SSSIs
2
(1)
Sub-paragraph (2) applies where—
(a)
(b)
a developer has committed to pay, in respect of a development, such amount of the nature restoration levy set out in a charging schedule to the EDP as applies in relation to an environmental impact of the development on that protected feature.
(2)
The environmental impact of the development on the protected feature is to be disregarded for the purposes of—
(a)
a determination by Natural England on whether to give consent (and if so on what terms) under section 28E of the Wildlife and Countryside Act 1981 or withdraw or modify any such consent,
(b)
a determination by the Secretary of State of an appeal under section 28F of that Act (appeals in connection with consents),
(c)
section 28H of that Act (statutory undertakers etc: duty in relation to carrying out operations),
(d)
section 28I of that Act (statutory undertakers etc: duty in relation to authorising operations), and
(e)
section 28P(2) and (5A) of that Act (offences in connection with sections 28H and 28I of that Act).