Legislation – Historic Environment (Wales) Act 2023
Which version?
Latest available (Revised)
Original (As enacted)
Changes to legislation:
Historic Environment (Wales) Act 2023, Cross Heading: Temporary listing is up to date with all changes known to be in force on or before 05 November 2025. There are changes that may be brought into force at a future date. Changes that have been made appear in the content and are referenced with annotations.![]()
Changes to Legislation
Revised legislation carried on this site may not be fully up to date. Changes and effects are recorded by our editorial team in lists which can be found in the ‘Changes to Legislation’ area. Where those effects have yet to be applied to the text of the legislation by the editorial team they are also listed alongside the legislation in the affected provisions. Use the ‘more’ link to open the changes and effects relevant to the provision you are viewing.
Changes and effects yet to be applied to Part 3 Chapter 1 Crossheading Temporary-listing:
- s. 11(3) inserted by 2024 asc 3 Sch. 3 para. 15(2)
- s. 58(4)(c) inserted by 2024 asc 3 Sch. 3 para. 15(3)
- s. 88(4) inserted by 2024 asc 3 Sch. 3 para. 15(4)
- s. 118(2)(f) inserted by 2024 asc 3 Sch. 3 para. 15(5)
- s. 161(6) inserted by 2024 asc 3 Sch. 3 para. 15(6)
Changes and effects yet to be applied to the whole Act associated Parts and Chapters:
Whole provisions yet to be inserted into this Act (including any effects on those provisions):
- s. 11(3) inserted by 2024 asc 3 Sch. 3 para. 15(2)
- s. 58(4)(c) inserted by 2024 asc 3 Sch. 3 para. 15(3)
- s. 88(4) inserted by 2024 asc 3 Sch. 3 para. 15(4)
- s. 118(2)(f) inserted by 2024 asc 3 Sch. 3 para. 15(5)
- s. 161(6) inserted by 2024 asc 3 Sch. 3 para. 15(6)
PART 3BUILDINGS OF SPECIAL ARCHITECTURAL OR HISTORIC INTEREST
CHAPTER 1LISTING BUILDINGS OF SPECIAL INTEREST
Temporary listing
83Service of temporary listing notice
(1)
This section applies if a planning authority considers that a building in its area which is not a listed building (and is not treated as one by virtue of section 79(2)) is—
(a)
of special architectural or historic interest, and
(b)
in danger of being demolished or of being altered in a way that would affect its character as a building of special architectural or historic interest.
(2)
The authority may serve a temporary listing notice on every owner and occupier of the building.
(3)
A temporary listing notice is a notice which—
(a)
states that the planning authority—
(i)
considers the building to be of special architectural or historic interest, and
(ii)
has requested the Welsh Ministers to consider listing it, and
(b)
explains the effect of subsection (4), section 85 and Schedule 7.
(4)
As soon as a temporary listing notice has been served on every owner and occupier of the building to which it relates, this Act (except sections 118 and 137 to 142) and the Town and Country Planning Act 1990 (c. 8) have effect in relation to the building as if it were a listed building.
(5)
The protection conferred by virtue of subsection (4) is referred to in this Part as “temporary listing”.
(6)
This section and section 84 do not apply to—
(a)
a building which is a scheduled monument, or
(b)
an exempt religious building.
84Temporary listing in urgent cases
(1)
This section applies if a planning authority considers it urgent that temporary listing should take effect in relation to a building in its area.
(2)
The authority may, instead of serving a temporary listing notice on each owner and occupier of the building—
(a)
attach the notice conspicuously to the building, or
(b)
if it is not reasonably practicable to attach the notice to the building, or the authority considers that doing so might damage the building, display the notice in a prominent place as near to the building as is reasonably practicable.
(3)
Attaching or displaying a notice in accordance with subsection (2) is to be treated for the purposes of section 83(4) as serving the notice on every owner and occupier of the building.
(4)
The notice must explain that by virtue of having been attached or displayed in accordance with subsection (2) the notice is treated as having been served for those purposes.
85End of temporary listing
(1)
Temporary listing of a building has effect until the end of the 6 months beginning with the day it takes effect under section 83(4), unless it ends under subsection (2) or (3).
(2)
If the Welsh Ministers serve notice under section 78(1) of a proposal to list the building, temporary listing ends when interim protection takes effect in relation to the building (and the building continues to be treated as if it were a listed building for certain purposes by virtue of section 79(2)).
(3)
If the Welsh Ministers notify the planning authority in writing that they do not intend to consult under section 78 on a proposal to list the building, temporary listing ends at the beginning of the day specified in the notification.
(4)
Schedule 7 makes provision about the effect of temporary listing coming to an end—
(a)
at the end of the 6-month period mentioned in subsection (1), or
(b)
because the Welsh Ministers give notification under subsection (3) that they do not intend to consult on a proposal to list the building.
(5)
If temporary listing ends in relation to a building because the Welsh Ministers notify the planning authority that they do not intend to consult on a proposal to list the building—
(a)
the authority must immediately give notice of that decision to every owner and occupier of the building;
(b)
the authority may not serve another temporary listing notice in respect of the building during the 12 months beginning with the day the Welsh Ministers give the notification.
86Compensation for loss or damage caused by temporary listing
(1)
This section applies where temporary listing ends in relation to a building—
(a)
at the end of the 6-month period mentioned in section 85(1), or
(b)
because the Welsh Ministers give notification under section 85(3) that they do not intend to consult on a proposal to list the building.
(2)
Any person who had an interest in the building when the temporary listing took effect is entitled, on making a claim to the planning authority in whose area the building is situated, to be paid compensation by the authority for any loss or damage suffered by the person that is directly attributable to the temporary listing.
(3)
The loss or damage for which compensation is payable includes any amount payable by the claimant in respect of a breach of contract caused by the need to stop or cancel works to the building because of the temporary listing.
(4)
A claim for compensation under this section must be made in writing within 6 months beginning when the temporary listing ends.