Legislation – Historic Environment (Wales) Act 2023
Changes to legislation:
Historic Environment (Wales) Act 2023, Section 107 is up to date with all changes known to be in force on or before 06 November 2025. There are changes that may be brought into force at a future date. Changes that have been made appear in the content and are referenced with annotations.![]()
Changes to Legislation
Revised legislation carried on this site may not be fully up to date. Changes and effects are recorded by our editorial team in lists which can be found in the ‘Changes to Legislation’ area. Where those effects have yet to be applied to the text of the legislation by the editorial team they are also listed alongside the legislation in the affected provisions. Use the ‘more’ link to open the changes and effects relevant to the provision you are viewing.
Changes and effects yet to be applied to Section 107:
- s. 11(3) inserted by 2024 asc 3 Sch. 3 para. 15(2)
- s. 58(4)(c) inserted by 2024 asc 3 Sch. 3 para. 15(3)
- s. 88(4) inserted by 2024 asc 3 Sch. 3 para. 15(4)
- s. 118(2)(f) inserted by 2024 asc 3 Sch. 3 para. 15(5)
- s. 161(6) inserted by 2024 asc 3 Sch. 3 para. 15(6)
Changes and effects yet to be applied to the whole Act associated Parts and Chapters:
Whole provisions yet to be inserted into this Act (including any effects on those provisions):
- s. 11(3) inserted by 2024 asc 3 Sch. 3 para. 15(2)
- s. 58(4)(c) inserted by 2024 asc 3 Sch. 3 para. 15(3)
- s. 88(4) inserted by 2024 asc 3 Sch. 3 para. 15(4)
- s. 118(2)(f) inserted by 2024 asc 3 Sch. 3 para. 15(5)
- s. 161(6) inserted by 2024 asc 3 Sch. 3 para. 15(6)
PART 3BUILDINGS OF SPECIAL ARCHITECTURAL OR HISTORIC INTEREST
CHAPTER 2CONTROL OF WORKS AFFECTING LISTED BUILDINGS
Modification and revocation of listed building consent
107Modification and revocation of consent
(1)
Where listed building consent has been granted on an application or appeal under this Part, the planning authority in whose area the listed building is situated or the Welsh Ministers may by order modify or revoke the consent to any extent.
(2)
An order modifying or revoking listed building consent for any works may be made at any time before the works are completed, but does not affect consent for works carried out before the order takes effect.
(3)
In Schedule 8—
(a)
Part 1 makes provision about the procedures that must be followed before an order made by a planning authority under this section takes effect (either with or without confirmation by the Welsh Ministers);
(b)
Part 2 makes provision about the procedure that must be followed before the Welsh Ministers make an order under this section.