Legislation – Historic Environment (Wales) Act 2023
Which version?
Latest available (Revised)
Original (As enacted)
Changes to legislation:
Historic Environment (Wales) Act 2023, Cross Heading: Grant of scheduled monument consent subject to conditions is up to date with all changes known to be in force on or before 07 November 2025. There are changes that may be brought into force at a future date. Changes that have been made appear in the content and are referenced with annotations.![]()
Changes to Legislation
Revised legislation carried on this site may not be fully up to date. Changes and effects are recorded by our editorial team in lists which can be found in the ‘Changes to Legislation’ area. Where those effects have yet to be applied to the text of the legislation by the editorial team they are also listed alongside the legislation in the affected provisions. Use the ‘more’ link to open the changes and effects relevant to the provision you are viewing.
Changes and effects yet to be applied to Part 2 Chapter 3 Crossheading Grant-of-scheduled-monument-consent-subject-to-conditions:
- s. 11(3) inserted by 2024 asc 3 Sch. 3 para. 15(2)
- s. 58(4)(c) inserted by 2024 asc 3 Sch. 3 para. 15(3)
- s. 88(4) inserted by 2024 asc 3 Sch. 3 para. 15(4)
- s. 118(2)(f) inserted by 2024 asc 3 Sch. 3 para. 15(5)
- s. 161(6) inserted by 2024 asc 3 Sch. 3 para. 15(6)
Changes and effects yet to be applied to the whole Act associated Parts and Chapters:
Whole provisions yet to be inserted into this Act (including any effects on those provisions):
- s. 11(3) inserted by 2024 asc 3 Sch. 3 para. 15(2)
- s. 58(4)(c) inserted by 2024 asc 3 Sch. 3 para. 15(3)
- s. 88(4) inserted by 2024 asc 3 Sch. 3 para. 15(4)
- s. 118(2)(f) inserted by 2024 asc 3 Sch. 3 para. 15(5)
- s. 161(6) inserted by 2024 asc 3 Sch. 3 para. 15(6)
PART 2MONUMENTS OF SPECIAL HISTORIC INTEREST
CHAPTER 3CONTROL OF WORKS AFFECTING SCHEDULED MONUMENTS
Grant of scheduled monument consent subject to conditions
18Power to grant consent subject to conditions
(1)
Scheduled monument consent may be granted subject to conditions.
(2)
A condition may, for example—
(a)
impose requirements with respect to the way in which or the persons by whom the works or any of the works are to be carried out;
(b)
require that a person authorised by the Welsh Ministers be given an opportunity, before any works start, to examine the monument and its site and to carry out such excavations as the Welsh Ministers consider to be desirable for the purpose of archaeological investigation.
19Condition about period within which works must start
(1)
Scheduled monument consent must be granted subject to the condition that the works to which it relates must start before the end of a period which is specified in the condition and begins with the day the consent is granted.
(2)
If consent is granted without the condition required by subsection (1), it is to be treated as having been granted subject to the condition that the works to which it relates must start within 5 years beginning with the day it was granted.
(3)
This section does not apply to—
(a)
scheduled monument consent which provides that it ceases to have effect at the end of a period specified in the consent (irrespective of whether any works have started),
(b)
consent granted under section 13(2) (consent for works already carried out), or
(c)
consent granted by a scheduled monument partnership agreement or a management agreement (see sections 25 and 51).